How Do I Access View Settings?
Phill Rodgers avatar
Written by Phill Rodgers
Updated over 5 years ago

View settings can be accessed using the 3-gears icon located in the top left of the Schedule page.

Tip

To change the default Schedule view of 1 week to more, click on the funnel icon in the top left of the Schedule and change the 'View' from 1 week up to 4 weeks, then click 'OK' to save the changes.

On the Activity page the view settings can be accessed by clicking on the 3 dots icon in the top right.

The view settings gives you options to choose from such as the start and end time of a day, time format, date format, the default event length and what colour picker you wish to use.

Tip

If your business is open between e.g. 7am to 7pm, set your view setting to start at 7:00 and end at 19:00.